Allenstown, Merrimack County
Two new secondary clarifiers at the wastewater plant (design)
Funding recipient: Allenstown
What the funding paid for
The funding recipient used the funding to design two new secondary clarifiers at the WWTF.
Funding
$225,000
- American Rescue Plan Act of 2021: $225,000
- Commitment date: Nov. 22, 2022
- Project type: Infrastructure (Construction)
- Water system: Wastewater
- Project number: 334104-01
- Location: Town center
- Record source: NHDES sample, Addendum 4