Epping, Rockingham County
Wastewater Treatment Facility Infiltration and Inflow Study
Funding recipient: Epping
What the funding paid for
The goal of this project includes evaluating and developing a plan to provide recommendations for improvements to reduce infiltration and inflow from the wastewater treatment facility in order to reduce hydraulic peaks to the plant.
Funding
$100,000
- Clean Water State Revolving Fund: $100,000
- Commitment date: June 4, 2025
- Project type: Planning
- Water system: Wastewater
- Project number: 247-08
- Location: Approximate
- Record source: EPA public records