Maine
Where the state’s revolving fund money for water went, project by project.
$505 million committed to 310 drinking water and clean water projects.
- Drinking water: $139 million
- Clean water: $365 million
- Grants and forgiven principal: $88.4 million
- Latest agreement: June 18, 2025
The 25 largest projects
- Davis Brook CSO Tank: Bangor, City of. $17.0 million, clean water, $1.0 million in grants and forgiven principal. Feb. 9, 2022. This project entails the construction of a 3.8 MG CSO storage tank under Bangor's waterfront park in the Davis Brook CSO sub-area. This project is expected to reduce CSO discharge by 12 MG per year.
- Wastewater Treatment Facility & Collection Systems Upgrades - Construction: Old Orchard Beach. $15.0 million, clean water. March 9, 2022. Upgrades to the WWTF and collection system.
- Route 236 Extension: Eliot, Town of. $14.1 million, clean water, $45,000 in grants and forgiven principal. June 5, 2024. This project is an extension of the sewer collection system through sections of Eliot to reduce the number of septic systems required throughout town. In addition to the new sewer collection lines two new pump stations…
- Water Resource Recovery Facility Upgrades: Saco, City of. $11.0 million, clean water. Sept. 26, 2024. This project entails a complete upgrade of the City of Saco's Water Resource Recovery Facility (WRRF). The drivers for this project include aging infrastructure and equipment, improved climate resiliency at the City's…
- Water Resource Recovery Facility Upgrades: Saco, City of. $11.0 million, clean water, $1.0 million in grants and forgiven principal. July 5, 2023. This project entails a complete upgrade of the City of Saco's Water Resource Recovery Facility (WRRF). The drivers for this project include aging infrastructure and equipment, improved climate resiliency at the City's…
- North Windham Wastewater Treatment Facility: Portland Water District. $11.0 million, clean water, $800,000 in grants and forgiven principal. Jan. 11, 2023. This project is constructing a centralized WWTF for the North Windham area, and the collection system for the Phase I planning area. The area currently has no centralized treatment and relies on private septic systems.…
- Water Resource Recovery Facility Upgrades: Saco, City of. $10.0 million, clean water. Jan. 27, 2025. This project entails a complete upgrade of the City of Saco's Water Resource Recovery Facility (WRRF). The drivers for this project include aging infrastructure and equipment, improved climate resiliency at the City's…
- North Windham Wastewater Treatment Facility: Portland Water District. $10.0 million, clean water, $1.4 million in grants and forgiven principal. Sept. 15, 2023. This project is constructing a centralized WWTF for the North Windham area, and the collection system for the Phase I planning area. The area currently has no centralized treatment and relies on private septic systems.…
- CSO Storage Tank: LAWPCA. $10.0 million, clean water. Jan. 21, 2025. This project includes construction of a 2.1 MG CSO storage tank as well as increasing maximum flow to the treatment plant to 38 MGD via influent pumping upgrades and new process control instrumentation. It is included…
- Bedford and Preble Streets CSO Sewer Separation: Portland, City of. $9.3 million, clean water. March 9, 2021. Sewer Separation for CSO Abatement
- Sewer and Storm Drainage Improvements, with Pump Station Upgrades: Ellsworth, City of. $8.7 million, clean water. June 27, 2024. Replacement of approximately 116,000 linear feet of sewer line (including manholes) and 80,000 linear feet of storm drain line (including catch basins and manholes), as well as upgrades to the High Street Pump Station…
- Wastewater Treatment Facility & Collection Systems Upgrades - Architecture and Engineering: Old Orchard Beach. $8.5 million, clean water. March 9, 2022. Upgrades to wastewater treatment facility and collection system - architecture and engineering services.
- Westbrook WWTF Aeration and Secondary Clarification Upgrade- loan 1: Portland Water District. $8.0 million, clean water. May 19, 2022. This project will replace the aeration system and secondary clarifier mechanisms, as well as upgrade the electrical and control system to provide resiliency and flexibility of treatment. The new aeration system will…
- Middle Road Transmission Main: Bath Water District, Bath. $7.4 million, drinking water, $2.2 million in grants and forgiven principal. May 12, 2023. Middle Road Transmission Main
- Back Cove West Conduit: Portland, City of. $7.1 million, clean water. May 25, 2023. Construction of the Back Cove West Storage Conduit to address storage needs, particularly in wet weather events.
- Headworks and Secondary Clarifiers Upgrade: Kennebunk Sewer District. $7.1 million, clean water. Feb. 1, 2019. Upgrade of Headworks Equipment and Secondary Clarifiers at Treatment Plant
- Main WWTF and Dix Ave PS Upgrade: Rumford-Mexico Sewerage District. $6.7 million, clean water, $210,000 in grants and forgiven principal. May 31, 2024. The Wastewater Treatment Facility upgrades. See C230104-03B for details.
- Back Cove West Conduit: Portland, City of. $6.4 million, clean water. Dec. 22, 2022. Construction of the Back Cove West Storage Conduit to address storage needs, particularly in wet weather events.
- Galvanized Service Lines Replacement: Portland Water District, Portland. $5.7 million, drinking water, $3.1 million in grants and forgiven principal. May 23, 2025. Replacement of 12,000 feet (+/-) of galvanized service lines less than 3-inch diameter installed pre-1930 downstream of lead connections
- East End WWTF-Treatment Plant and Northeast Pump Station Electrical Upgrade: Portland Water District. $5.2 million, clean water. Sept. 22, 2022. East End treatment plant and Northeast pump station electrical system upgrades.
- North Windham Wastewater Treatment Facility: Portland Water District. $5.0 million, clean water, $689,000 in grants and forgiven principal. March 17, 2025. This project is constructing a centralized WWTF for the North Windham area, and the collection system for the Phase I planning area. The area currently has no centralized treatment and relies on private septic systems.…
- North Windham Wastewater Treatment Facility: Portland Water District. $5.0 million, clean water, $311,000 in grants and forgiven principal. March 17, 2025. This project is constructing a centralized WWTF for the North Windham area, and the collection system for the Phase I planning area. The area currently has no centralized treatment and relies on private septic systems.…
- Water Resource Recovery Facility Upgrades: Saco, City of. $5.0 million, clean water. Sept. 26, 2024. This project entails a complete upgrade of the City of Saco's Water Resource Recovery Facility (WRRF). The drivers for this project include aging infrastructure and equipment, improved climate resiliency at the City's…
- Water Resource Recovery Facility Upgrades: Saco, City of. $5.0 million, clean water. Jan. 27, 2023. This project entails a complete upgrade of the City of Saco's Water Resource Recovery Facility (WRRF). The drivers for this project include aging infrastructure and equipment, improved climate resiliency at the City's…
- West Falmouth Sewer Improvements - Construction: Falmouth, Town of. $5.0 million, clean water. June 10, 2022. Replace and install new sewer lines
Counties that received the most
- York: $120 million
- Cumberland: $61.4 million
- Penobscot: $45.2 million
- Kennebec: $33.1 million
- Androscoggin: $23.1 million
- Piscataquis: $21.4 million
- Aroostook: $20.3 million
- Waldo: $17.6 million
- Oxford: $13.4 million
- Sagadahoc: $13.0 million
Every project, with filters, a map and a table, is on this page in the app. Source: EPA State Revolving Fund public records, through June 30, 2025.
All states · About the data · New Hampshire concept · Consul, Inc.